I just wanted to give you all a little update about our
process in implementing our new Student Information System (SIS). Here are some
of the things we’ve done since you last heard from me:
- All
contracts were negotiated and signed and POs were drawn up
- Last
week, the Infinite Campus Sales Team wanted to meet with me, our head of
IT (Jesse), Preeti and our Schedulers. We met for about 90 minutes online
and they asked for some basic information about bell schedules and
attendance protocols and the primary purpose of the meeting was to
introduce us to our Implementation Project Manager, Katie Groth, as well
as the team of four others from Infinite Campus who will be supporting our
transition.
- We
created an Implementation Team made of the following people, because they
fit the types of roles Infinite Campus indicated would be most helpful:
- Me,
Jesse Lara, Jennifer Gargano, Preeti Sharan, Kristin Giammona, Evan
Barth, Lori Villarreal, Marianne Rager, Troy Thiele
- The
SIS Success Team is still an integral part to our entire process, and will
continue to be used as a resource as specific implementation questions
arise.
- This Implementation Team will be meeting with all of Infinite Campus’ Team in early November, after which I will provide an additional update about more specific details.
(This blogpost was also sent to AllHarker on 10/19/18)